home *** CD-ROM | disk | FTP | other *** search
/ Apple Reference & Presen…rary 6 (Reseller Edition) / Apple Ref. & Pres. Lib.v6.0.toast / pc / 5-Fonts & Software / Applications / MacProject II / MacProject II Help / card_39404.txt < prev    next >
Text File  |  1989-09-27  |  2KB  |  80 lines

  1. -- card: 39404 from stack: in
  2. -- bmap block id: 39715
  3. -- flags: 0000
  4. -- background id: 3633
  5. -- name: Elapsed Time
  6.  
  7.  
  8. -- part 38 (field)
  9. -- low flags: 01
  10. -- high flags: 0000
  11. -- rect: left=245 top=69 right=155 bottom=321
  12. -- title width / last selected line: 0
  13. -- icon id / first selected line: 0 / 0
  14. -- text alignment: 0
  15. -- font id: 3
  16. -- text size: 9
  17. -- style flags: 0
  18. -- line height: 12
  19. -- part name: callout
  20.  
  21.  
  22. -- part 39 (button)
  23. -- low flags: 00
  24. -- high flags: A003
  25. -- rect: left=12 top=243 right=266 bottom=239
  26. -- title width / last selected line: 0
  27. -- icon id / first selected line: 0 / 0
  28. -- text alignment: 1
  29. -- font id: 3
  30. -- text size: 10
  31. -- style flags: 0
  32. -- line height: 13
  33. -- part name: Specifying Attributes for the Schedule Chart 
  34. ----- HyperTalk script -----
  35. on mouseUp
  36.   go card id 2228
  37. end mouseUp
  38.  
  39.  
  40. -- part contents for background part 6
  41. ----- text -----
  42. The elapsed time for a task is the amount of calendar time the task takes, plus any nonworking time.
  43.  
  44. For example, suppose it takes three days to prepare drawings (duration) and you begin work on Friday, October 21 (Earliest 
  45. Start). With the usual Monday through Friday work week, the elapsed time for the task would be 5 days.
  46.  
  47. These attributes can all be displayed in the Schedule Chart.
  48.  
  49.  
  50.  
  51.  
  52. -- part contents for background part 7
  53. ----- text -----
  54.  
  55.  
  56.  
  57.  
  58.  
  59.  
  60.  
  61.  
  62.  
  63. Duration and elapsed time are also shown in the Project Table. The charts that are based on a span of time‚Äîthe Resource Timeline, Task Timeline, and Resource Histogram‚Äîgive their information in elapsed time.
  64.  
  65. -- part contents for background part 27
  66. ----- text -----
  67. Schedule Information
  68.  
  69. -- part contents for background part 28
  70. ----- text -----
  71. Elapsed Time
  72.  
  73. -- part contents for card part 38
  74. ----- text -----
  75. Duration
  76.  
  77. Earliest Start date
  78.  
  79.  
  80. Elapsed time